Project Milestone |
Description (Days from Appointed Date ) |
Planned | Actual | Delay (No. of months) | Current Physical Status |
||
---|---|---|---|---|---|---|---|
Physical Status Progress (%) |
Scheduled Date | Physical Progress (%) |
Achieved Date | ||||
Milestone I | 23rd July 2018 (290th days) | 20% | 23rd July 2018 | 20.53% | Nil | 31st May 2018 1st Milestone Achieved 53 days ahead of Milestone Scheduled date | |
Milestone II | 10th December 2018 (430th days) | 35% | 10th December 2018 | 35.44% | Nil | 3rd October 2018 2nd Milestone Achieved 68 days ahead of Milestone Scheduled date | |
Milestone III | 27th August 2019 (690th days) | 75% | 27th August 2019 | 76.16 % | Nil | 20th August 2019 3rd Milestone Achieved 07 days ahead of Milestone Scheduled date. | |
Scheduled Completion |
3rd April 2020 (910th days) | 100% | 3rd April 2020 | 84.65 % | – | Project work is under progress |