banner

Project Milestones

Project Milestones

Project
Milestone
Description
(Days from
Appointed
Date )
Planned Actual Delay (No. of months) Current
Physical Status
Physical Status
Progress (%)
Scheduled Date Physical
Progress (%)
Achieved Date
Milestone I  23rd July 2018 (290th days) 20% 23rd July 2018 20.53% Nil 31st May 2018 1st Milestone Achieved 53 days ahead of Milestone Scheduled date
Milestone II  10th December 2018 (430th days) 35% 10th December 2018 35.44% Nil 3rd October 2018 2nd Milestone Achieved 68 days ahead of Milestone Scheduled date
Milestone III  27th August 2019 (690th days) 75% 27th August 2019 76.16 % Nil 20th August 2019 3rd Milestone Achieved 07 days ahead of Milestone Scheduled date.
Scheduled
Completion
 3rd April 2020 (910th days) 100% 3rd April 2020 84.65 % Project work is under progress